Latest Site Updates

Project Development Work in Progress

Development work at Vinrise, Machilipatnam is progressing steadily. The compound wall and painting work have been completed, while entrance arch construction, road leveling, and underground drainage pipe installation are currently underway. Plantation work has also been completed, adding greenery to the project.

The project is taking shape step by step with ongoing infrastructure and site development works.

Compound Wall

100% Completed

Plantation

100% Completed

Entrance Arch

85% Completed

UnderGround Drainage

60% Completed

Road Leveling

60% Completed